Amendment No.15
Amendment No.15: Clarify the operation of the roll-over provision for housing delivery between development areas
Amend 4.7 of the Planning Scheme to clarify that the 250 units in the ‘Roll Over’ provision can be occupied.
It is proposed that a change be made to section 4.7 of the Planning Scheme, Operation of Phasing Programme, to provide clear guidance that up to 250 dwelling units permitted under the Roll-Over mechanism may be both constructed and occupied. This provides flexibility while maintaining alignment with the phasing principles of the Planning Scheme.
| Amendment Ref. No. 15 | |
| Section Reference | Page Reference (2019 Planning Scheme) |
| 4.7 Operation of Phasing Programme | 140 |
Edit text in relation to the last paragraph in Section 4.7:
A ‘Roll - Over’ mechanism may operate between any two phases. In the event of the maximum permissible number of units being completed before the required facilities and infrastructure in any phase, a ‘Roll - Over’ of up to 250 dwelling units may be constructed and occupied in the following phase, subject to planning permission. These residential units may not be constructed until the developer demonstrates the provision of requirements from the previous phase is ongoing and the units may not be occupied until the requirements in the previous phase have been completed.