Litir Chumhdaigh

We, Marston Planning Consultancy, 23 Grange Park, Foxrock, Dublin, D18 T3Y4 are instructed by our client Vantage Data Centers DUB 11 Ltd. with a registered address at 1-2 Victoria Buildings, Haddington Road, Dublin 4 to make a formal submission on the provisions of the Proposed Material Amendments of the South Dublin Draft County Development Plan 2022-2028. This submission is accompanied by a legal opinion on the Proposed Amendments by Jarlath Fitzsimons SC. This sets out the legal case and statutory provisions of the need for the adopted South Dublin County Development Plan 2022-2028 to be consistent with the National Planning Framework (NPF) and the Eastern and Midland Regional Assembly Regional Spatial and Economic Strategy 2019 (EMRA RSES).

Observations

Chapter 13: Implementation and Monitoring

Select Proposed Amendment on which you are commenting: 

To amend Proposed Amendments 13.1, 13.2 and 13.3 as follows:

  1. To amend Proposed Amendment 13.1 and Amend Table 13.4 Zoning Objective ‘REGEN’ so that ‘Data Centre’ is moved from being ‘Not Permitted’ to being ‘Open for Consideration’.
  2. To amend Proposed Amendment 13.2 and Amend Table 13.9 Zoning Objective ‘MRC’ so that ‘Data Centre’ is moved from being ‘Not Permitted’ to being ‘Open for Consideration’.
  3. To amend Proposed Amendment 13.3 and Amend Table 13.10 Zoning Objective ‘EE’ so that ‘Data Centre’ is moved from being ‘Not Permitted’ to being ‘Open for Consideration’.

We would refer the Council to the fact that it is not current policy either of EirGrid or the Government to restrict data centre development in any form and the Proposed Amendments are in direct conflict with both the NPF and RSES.  However, as we have demonstrated under this submission, there are a range of criteria under which EirGrid will consider in providing power and connections to data centres that will each be considered on their individual merit.  There is clearly an intrinsic link between power and data centre development and this is recognised in current policy set out by the CRU and EirGrid.  This is reflected in Policy EDE7 Objective 2 of the Draft Plan that is also amended under the Material Alterations.

We respectfully submit, for reasons that are set out under this submission, that there is no basis for making data centres ‘not permitted’ uses under the Material Alterations of the Draft Plan. On that basis we would request that South Dublin County Council reverse its Proposed Amendments 13.1, 13.2 and 13.3 under the Material Alterations as outlined above.